Northeast Quadrant Trunkline

The sewer District needed a large diameter outfall from growing areas along the east side of the District to the wastewater treatment plant (WWTP). We designed, bid, and oversaw the construction of 30,000 feet of 12 to 24-inch sewer main. This project involved a 200 foot long horizontal boring beneath a highway. Slope control was critical during construction because the slopes on the pipes were very small.